Donetsk Metro

The Donetsk Metro (Ukrainian: Донецьке метро, translit.: Donets'ke metro; Russian: Донецкое метро, translit.: Donetskoe metro) is a future underground rapid transit system in Donetsk, construction of which is currently abandoned due to lack of funding. If finished, it will become the fourth metro in Ukraine (after the Kiev, Kharkiv and Dnipropetrovsk metros). A development plan announced earlier calls for 3 lines and 22 stations, with all lines crossing in the center of the city, and also two lines crossing in suburban areas.

History

When the city of Donetsk reached the million inhabitants mark in the 1980s, it was entitled to build its own metro system, which was designed to follow the usual layout in the Soviet Union. In 1984 the first plans for a metro system in Donetsk were shown to the public, but construction did not immediately begin. Only after Ukraine gained independence, the Cabinet of Ministers issued a decree on 30 December 1991 to build the new underground metro system in Donetsk. The first investigation work began in 1992, and construction commenced the same year, with completion scheduled for 2002.

In 1995, due to the poor financial situation of the Donetsk municipality, the completion date was postponed to 2005. On September 5, 1997, the Prime Minister of Ukraine, Valeriy Pustovoitenko, ordered that the first line of the system should be open to the public in 8 years (2005). In 2000, the first work on four of the six underground stations began. However, the financial situation of Donetsk did not improve. In June 2003, the financial problems affected the metro workers - after seven months of work, no more wages could be paid. By then nearly 300 million Hryven (about 48 million euros) had been spent on the project.

Donetsk Metro
Politekhnichnyi Institut
Livoberezhna
Mushketovska
Chervone Mistechko
Chumakovska
Proletarska
edit

In 2004 the Ukrainian government assured further means for the completion of the metro by 2010. By 2007 this seemed over-optimistic due to the slow pace of construction work. However, it later emerged that Donetsk would be one of the host cities for the Euro 2012 football championships, raising hopes for the Metro to be opened by then, although the budget that had been allocated was clearly insufficient at the time.

In 2009 funding of the project was disrupted so severely that construction workers staged several strikes to demand payment of their salaries.

In 2011 the city mayor announced that construction was to be suspended indefinitely due to continuing underfunding and inability to finish a first line in time for Euro 2012.

Future plans

The first underground line of the system, which will carry the name Proletarsko-Kyivs'ka Line (Ukrainian: Пролетарсько-Київська, Russian: Пролетарско-Киевская), is to be 9.6 km (6.0 mi) long and have six stations: Proletars'ka (Пролетарська), Chumakovs'ka (Чумаковська), Chervone Mistechko (Червоне мiстечко), Mushketovs'ka (Мушкетовська), Livoberezhna (Лiвобережна), and Politechnichnyi Institut (Полiтехнiчний iнститут).

The system's red line, Proletarsko-Kyivska, is planned to extend 21 km (13 mi) with 15 stations. Additionally, the blue line, Shakhtarsko-Makiyivs'ka Line (Ukrainian: Шахтарсько-Макiївська; Russian: Горняцко-Макеевская), is planned to extend 25 km (16 mi). Finally, the green line, Petrovs'ko-Chervonohvardiyska Line (Ukrainian: Петровсько-Червоногвардiйська; Russian: Петровско-Красногвардейская), is to have 14 stations. In its final stage, the Donetsk Metro is planned to be 70 km (43 mi) long, with a total of 46 stations.

External links

  • (English) [1] - Official Donetsk city guide
  • (Russian) metro.donetsk.ua - Unofficial Donetsk metro website

References